Efforts to complete disbursement of public investment capital
28/11/2023
According to Director of the Project Management Board for Construction Investment of Civil and Industrial Works in Long An province - Tran Ba Phuoc, the Board focuses on measures and solutions to ensure completion of the disbursement schedule of public investment capital according to plan.

giải ngân vốn đầu tư công 2023.jpg

The Project Management Board for Construction Investment of Civil and Industrial Works in Long An province ensures to complete the disbursement of public investment capital in 2023 (In photo: Basic Traditional Medicine Hospital project disbursement 85 percent of capital plan in 2023)

In 2023, the Board will be allocated nearly 570 billion VND to implement projects. By the end of November 16, 2023, the Board disbursed nearly 72 percent of public investment capital, of which, capital allocated before July 31, 2023, disbursed over 78 percent; Additional capital for the project of 70 commune-level medical stations (delivered on August 4, 2023), disbursed nearly 52 percent; Additional capital for 2 projects outside the medium-term capital plan (delivered on September 18, 2023), disbursed over 84 percent. The disbursement rate of public investment capital of the Board is still not high compared to the plan due to problems with site clearance, so the implementation of some projects is still slow; Sand prices increase, affecting progress; Capital allocation is slow.

The Board will focus fiercely and coordinate to remove obstacles, ensure project progress as well as capital disbursement; organize a review of the entire project, adjust capital accordingly; Disbursement according to each remaining month; Accelerate bidding progress for equipment packages (mainly medical equipment);... ensure completion of the proposed disbursement plan for public investment capital in 2023./.

Reported by Chau Son

Translated by NT

Lượt người xem:   66
Manage PermissionsManage Permissions
|
Version HistoryVersion History

Tiêu đề

Hình ảnh

Hình ảnh mô tả

Tóm tắt

Nội dung

Link thay thế nội dung

Ngày xuất bản

Tin nổi bật

Tác giả

Phân loại

Loại bài viết

Số Trang

Số Ảnh

Trạng thái

Lịch sử

Số lượt người đọc

Approval Status

Attachments

Content Type: Tin Tức Mở Rộng
Version:
Created at by
Last modified at by
LONG AN PORTAL
Line Agency: People's Committee of Long An Province
Standing agency: The People's Committee Office​
Direct instruction: Chief of Office of the Provincial People’s Committee – Vo Thanh Tri
Address: 61 Nguyen Hue, Ward 1, Tan An City, Long An Province
Phone: (0272). 3552489​
Email: vpubnd@longan.gov.vn; webmaster@longan.gov.vn
License No. 01 / GP-TTDT-STTTT dated March 3, 2015 - Department of Information and Communications