Accordingly,
the work of the ring road channel embankment (section from Nguyen Thong road to
Vam Co Tay River) was started on July 9, 2018, with total investment over 42.3
billion VND. Up to now, the basic works have completed all items, expected to
be put into use on August 15, 2019.
The
work of repairing Hung Vuong Avenue (section from National Highway 1 to Nguyen
Dinh Chieu street) started at the end of May 5, 2019, with a total investment
of 14.9 billion VND, it is expected to be completed before August 15, 2019.

The Clock Tower work at Vo Van Tan
Roundabout
The
Park of ward 2 has started leveling the ground site for planting grass; items
to decorate green areas around bridges of Bao Dinh, Truong Dinh and Duc; the
embankment area of Phan Van Dat street is continuing to be embellished; and so
on.
The
city invested and completed the Clock Tower work at the roundabout of Vo Van
Tan and Nguyen Trung Truc; Crystal Ball work with LED lighting at stadium
roundabout.

The Crystal Ball work with LED
lighting at stadium roundabout
Besides,
the provincial People's Committee agreed on the policy for the city to invest
in 2 works of highlight in the roundabout of ward 4 and ward 5, and the city is
implementing the procedures prescribed to implement the project in the soonest
time.
In
addition, the city People's Committee directed the Urban Management Division,
the Office of Culture and Information, the People's Committee of communes and
wards to concentrate on organizing inspection troops, handling urban order,
building and cleaning sanitation and embellishing routes in the city to ensure
urban landscape and beauty./.