Long An Province Power Development Plan for phase 2011 – 2015 with considerations to 2020 has the following main criteria: I. Power load The power load is calculated to meet the sufficient power demand for socio-economic development of Long An province with the GDP growth rate in Phase 2011 – 2015 of 14.0%/year; GDP growth rate in phase 2016-2020 of 13.3%/year.

he thong cap đien.jpg

- In 2015: It is estimated that the maximum capacity is Pmax= 772,3MW, the commercial power capacity is 4507.9 million kWh. The average growth rate of the commercial power in phase 2011-2015 is 20.2%/year.

- In 2020: It is estimated that the maximum power is Pmax=1528.0MW; the commercial power is 9,428.8 million kWh. The average growth rate of the commercial power in phase 2016 - 2020 is 15.9%/year.

II. Construction quantity

The estimated construction quantity in the project only consists of construction of the power network in the districts, city of Long An Province

1. 220, 110kV grids:

a- Phase 2011 - 2015:

- 220kV power line:

+ Newly constructing 70.7 km of power line

+ Improving 144.0 km of the power line

- 220kV Substation:

+ Increasing the capacity of the 220kV Long An 2 substation, (2x250)MVA

+ Newly constructing Duc Hoa 2 Sub-station 2 - (2x250)MVA

+  Newly constructing Ben Luc 2 Sub-station 2 - (1x250)MVA.

+ Newly constructing Can Duoc Sub-station - (1x250)MVA.

- 110kV grid:

+ Newly constructing 15 lines with the total length of 82.5km.

- 110kV Substation:

+ Newly constructing 15 transformers with the total capacity of 923MVA (in which there are 5 client substations with the total capacity of 305MVA including: Le Long substation: 40MVA, Xuyen A Industrial Park substation: 2x40 MVA, Vinh Loc 2 Substation: 40 MVA, Thuan Dao Industrial Park Substation 40+25MVA and Phu An Thanh Industrial Park Substation: 2x40MVA).

+ Improving and installing machines for 2 transformers, increasing the capacity for 5 transformers with the total capacity of 145MVA.

b- Phase 2016 - 2020:

- 220kV grid:

+ Newly constructing 2 lines with the total length of 32km.

- 220kV Substation:

+ Newly constructing 220kV Ben Luc 3 Substation - (2x250)MVA.

- 110kV grid:

+ Newly constructing 11 lines with the total length of 167.5km.

- 110kV Substation:

+ Newly constructing 8 transformers with the total capacity of 664MVA

+ Improving and installing machines for 2, increasing the capacity for 10 transformers with the total capacity of 710MVA

2. Distribution network:

a- Phase 2011 -- 2015:

- 22kV grid:

+ Newly constructed: 779.4 km

+ Improved: 505,5 km

- 22/0,4kV Transformer:

+ Newly constructing: the transformers with the total capacity of 588,572.5kVA

- Low voltage:

+ Newly constructing 1,260 km; installing 89,386 power meters

b- Phase 2016 - 2020:

- 22kV grid:

+ Newly constructed: 541.3 km

+ Improved: 252.7 km

- 22/0.4kV transformers:

+ Newly constructing the transformers with the total capacity of 353,143.5kVA

- Low voltage:

+ Newly constructing 756 km; installing 28,931 power meters

III. Investment capital

In phase 2011 – 2015, the total investment capital to be mobilized is VND 6,847,737 million

In which:

220kV grids:  VND3,809,470 million

110kV grids: VND1,851,100470 million

22kV grids: VND938,322 million

Low voltage grid: VND248,845 million

Total: VND6,847,737 million.​

Lượt người xem:   1703
Manage PermissionsManage Permissions
|
Version HistoryVersion History

Tiêu đề

Hình ảnh

Hình ảnh mô tả

Tóm tắt

Nội dung

Link thay thế nội dung

Ngày xuất bản

Tin nổi bật

Tác giả

Phân loại

Loại bài viết

Số Trang

Số Ảnh

Trạng thái

Lịch sử

Số lượt người đọc

Approval Status

Attachments

Content Type: Tin Tức Mở Rộng
Version:
Created at by
Last modified at by
LONG AN PORTAL
Line Agency: People's Committee of Long An Province
Standing agency: The National Assembly Delegation, the Provincial People's Council and People's Committee Office​
Direct instruction: Mr. Mai Van Nhieu - Chief of Staff of the National Assembly Delegation, the provincial People's Council and People's Committee
Address: 61 Nguyen Hue, Ward 1, Tan An City, Long An Province
Phone: (0272). 3552489​
Email: vpubnd@longan.gov.vn; webmaster@longan.gov.vn
License No. 01 / GP-TTDT-STTTT dated March 3, 2015 - Department of Information and Communications